THE City of Coffs Harbour (City) has invited the community to provide feedback on its draft Delivery Program (2025-2029) and Operational Plan (FY 25/26).
The Delivery Program and Operational Plan set out the City’s key projects and activities over the Council’s four-year term.
Capital asset projects of almost $64 million are contained within the draft Operational Plan for the 2025-26 financial year.
Acting General Manager Andrew Beswick said capital projects are prioritised based on the City’s capacity to deliver.
2025/26 capital projects include:
● New amenities at Len Towels Oval, Nana Glen, $840k
● Toormina Sports Complex new playing field, carpark and footpaths new amenities $720k
● Moonee Sports Complex feasibility study $50k
● Woolgoolga Pool heat pumps renewal $60k
● Annual Sewer Main Relining Project $1.1m
● North Boambee Valley flood detention basin $3.256m
● Stormwater drainage renewal program $1m
● Remediation of Loaders Lane Flood Levee (NSW Government Grant) $518k
● North Boambee Road road-raising and infrastructure works $7m
● O’Keefe Drive pavement renewal (design) $2.2m
● West Woolgoolga Newmans Rd Intersection $795k
● Upper Orara Way road culvert renewal $780k
● Arrawarra Beach Road road renewal $620k
● South Coffs Cycleways $273k
● First and Second Ave footpaths renewal, Sawtell, $130k
● Coffs Harbour Waste Transfer Station planning $500k
● Solitary Islands Way Water Main Duplication Project $1.5m
● Coffs Harbour Arthur St water main construction $1m; and
● New Coffs Harbour Laboratory $2m.
View the draft Delivery Program 2025-2029 and Operational Plan 2025/26 and provide feedback at https://haveyoursay.coffsharbour.nsw.gov.au/dpop.